The scope of this guide is to provide methodologies and practices for a systematic and coordinated approach for the development of requirements and specifications for turnkey substation projects.
- Standard Committee
- PE/SUB - Substations
- Status
- Active PAR
- PAR Approval
- 2020-02-13
- Superseding
- 1267-2019
Working Group Details
- Society
- IEEE Power and Energy Society
- Standard Committee
- PE/SUB - Substations
- Working Group
-
WGD8 - Development of Specification for Turnkey Substation Projects
Learn More About WGD8 - Development of Specification for Turnkey Substation Projects - IEEE Program Manager
- Patricia Roder
Contact Patricia Roder - Working Group Chair
- Michael Nadeau
Other Activities From This Working Group
Current projects that have been authorized by the IEEE SA Standards Board to develop a standard.
No Active Projects
Standards approved by the IEEE SA Standards Board that are within the 10-year lifecycle.
1267-2019
IEEE Guide for Development of Specifications for Turnkey Substation Projects
Systematic methodology, guidelines and practices for developing turnkey substation specifications are provided in this guide. Guidance on engineering, procurement, construction, testing and commissioning, quality assurance/quality control and training is provided.
These standards have been replaced with a revised version of the standard, or by a compilation of the original active standard and all its existing amendments, corrigenda, and errata.
No Superseded Standards
These standards have been removed from active status through a ballot where the standard is made inactive as a consensus decision of a balloting group.
No Inactive-Withdrawn Standards
These standards are removed from active status through an administrative process for standards that have not undergone a revision process within 10 years.
No Inactive-Reserved Standards